Construction of Sovereign’s rutile-graphite pilot phase on schedule

Estimated read time 3 min read

Kasiya’s pilot mining and land rehabilitation program underway with site establishment on schedule
Project is the world’s largest natural rutile deposit and the second-largest flake graphite deposit
Mobile fleet is currently constructing the test pit, water storage pond and ore stockpile
Key contractors and consultants across major disciplines have been appointed

 

Special Report: Sovereign Metals says site construction for the ongoing pilot mining and land rehabilitation program at the Kasiya Rutile-Graphite Project in Malawi is on schedule with groundworks underway.

Kasiya is the world’s largest natural rutile deposit and the second-largest flake graphite deposit.

Sovereign (ASX:SVM) aims to develop the advanced project into a low-CO2, sustainable operation to supply highly sought-after natural rutile and natural graphite to the global markets.

The company is also aiming to restore land after mining to conditions that achieve the same, or better, agricultural yields than existing land uses and crop yields.

 

‘Ability to execute in Malawi’

The Pilot Phase will demonstrate to local communities the successful rehabilitation of land for agricultural use post-mining.

Plus, the results will also allow Sovereign to determine optimal excavation and backfill approaches, providing critical information for the upcoming Definitive Feasibility Study.

“This Pilot Phase is a step-change for Kasiya and demonstrates our ability to execute in Malawi,” managing director Frank Eagar said.

“The early works are progressing as planned: on schedule and within budget.

“We are very pleased with the progress and specifically how the mobile fleet is performing in the soft saprolite ore, confirming our understanding of how simple mining, with no drilling or blasting required, will contribute to low operating costs.”

 

Pic: Planned site layout. Source: SVM.

 

Key contractors on board

The construction fleet is on-site with groundwork to excavate the water storage pond and construct the test areas currently underway.

Key contractors and consultants have been appointed across all major disciplines essential for the Pilot Phase, including multinational engineering and construction company Mota Engil Group who will perform all excavation required for site establishment, the water storage pond, the test pit, seven rehabilitation pits, site closure and general rehabilitation of the site.

Importantly, the test pit of 120m by 110m will be excavated to a depth of 20m, allowing optimisation of hydraulic and dry mining excavation methods.

In addition, Sovereign will also construct eight small rehabilitation demonstration pits covering a combined area of 100m by 130m which will be used for water storage, excavated material storage, and demonstration of multiple rehabilitation approaches.

 

 

This article was developed in collaboration with Sovereign Metals, a Stockhead advertiser at the time of publishing.

 

This article does not constitute financial product advice. You should consider obtaining independent advice before making any financial decisions.

The post Construction of Sovereign’s rutile-graphite pilot phase on schedule appeared first on Stockhead.

You May Also Like